Mortgage release deadlines by state

After a mortgage is paid off, state law gives the lender a fixed time to record a satisfaction or release, from 10 days after a request in Minnesota to 90 days in Ohio, Montana and Virginia. Below are the deadline, what starts the clock, the penalty and the statute for 21 states, each read from the official code on October 15, 2026.

Mortgage satisfaction deadlines by state
StateDeadlineStartsIf the lender misses itStatute
Arizona30 daysafter receiving satisfaction of the mortgage or deed of trustLiable to the owner if still not recorded 30 days after a certified-mail requestA.R.S. § 33-712
Connecticut60 daysafter a written request sent by registered or certified mail$200 per week after the 60 days, up to $5,000, or actual damagesConn. Gen. Stat. § 49-8
Delaware60 daysafter the debt is satisfied (including any satisfaction fee)The recorder files a complaint with the Attorney General25 Del. C. § 2111
Florida60 daysafter the loan is paid in full (or paid under an estoppel letter)Statutory duty to execute and record the satisfactionFla. Stat. § 701.04(2)
Illinois30 daysafter payment of the debt$200 per offense to the aggrieved party765 ILCS 905/4
Iowa30 daysafter payment in fullStatutory duty to acknowledge and file the satisfactionIowa Code § 655.1
Kansas20 daysafter a written demand by certified or registered mail$500 in damages plus a reasonable attorney's feeK.S.A. § 58-2309a
Maine60 daysafter full performance of the mortgage$200 per week after the 60 days, up to $5,000, or actual loss33 M.R.S. § 551
Massachusetts45 daysafter receipt of full paymentLiable in damages to the mortgagorMass. Gen. Laws ch. 183, § 55
Minnesota10 daysafter a request and tender of reasonable chargesLiable for actual damagesMinn. Stat. § 507.41
Missouri45 daysafter a request and tender of costsDaily damages of up to $300 a day, subject to the statute's limitsMo. Rev. Stat. § 443.130
Montana90 daysafter a request for a certificate of discharge or releaseLiable to the mortgagorMont. Code § 71-1-212
Nevada21 calendar daysafter written notice that the debt was paidAfter 75 days a title insurer may record a release itselfNRS 106.260
New Hampshire60 daysafter the mortgage is satisfied and reasonable charges are tenderedStatutory duty to record the dischargeRSA 479:7
North Carolina30 daysafter the creditor receives full paymentStatutory duty to submit the satisfaction for recordingN.C. Gen. Stat. § 45-36.9
North Dakota10 daysafter a written demand once the balance is zeroThe discharge must then be recorded within 30 days of signingN.D. Cent. Code § 35-03-15
Ohio90 daysafter the mortgage is satisfiedAfter a further 15-day notice, $100 per day in damages plus feesOhio Rev. Code § 5301.36
Oregon30 daysafter a request and tender of reasonable chargesLiable to the mortgagorORS 86.140
South Carolina3 monthsafter a certified-mail request and tender of the recording feeA forfeiture payable to the person who askedS.C. Code § 29-3-310
Virginia90 daysafter payment, when no settlement agent handles it$500 forfeited to the borrower, plus court costs and fees if unpaid after demandVa. Code § 55.1-339
Washington60 daysafter a request or demand for the satisfactionDamages and a reasonable attorney's feeRCW 61.16.030

Not yet in the table: Alabama, Alaska, Arkansas, California, Colorado, District of Columbia, Georgia, Hawaii, Idaho, Indiana, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Nebraska, New Jersey, New Mexico, New York, Oklahoma, Pennsylvania, Rhode Island, South Dakota, Tennessee, Texas, Utah, Vermont, West Virginia, Wisconsin and Wyoming. Their official codes either block automated reading or render only in a browser, and we list a state only after reading its statute from the official source. More guidance on how a satisfaction works: satisfaction of mortgage and is that mortgage actually open?

Questions

How long does a lender have to release a mortgage after it is paid off?

It depends on the state: from 10 days after a request in Minnesota to 90 days in Ohio, Montana and Virginia. Florida, Delaware, Maine and New Hampshire allow 60 days; Illinois, Iowa, North Carolina and Arizona 30 days. The table lists 21 states with the statute for each.

What happens if the lender never records the release?

Many states set a penalty: $200 a week up to $5,000 in Connecticut and Maine, $500 in Kansas and Virginia, $100 a day in Ohio after notice. Until a release is recorded, the mortgage still shows as open in the county records and can delay a sale or refinance.

How do I check whether my mortgage release was recorded?

Search the county recorder or clerk for a satisfaction, release or reconveyance that cites your mortgage, or run a HeritageDeed report, which matches every recorded mortgage to its release and lists the ones still open.

Summaries of statutes read 2026-10-15, free to reuse under CC BY 4.0 with a link to this page. Not legal advice: read the statute and check for amendments before relying on a deadline.